COA blocks “soft opening” of Divisoria
Integrated Bus Terminal less overpass
City Administrator Antonio Orendain Jr said the City Government can not open “partially” the
Integrated Bus Terminal (IBT) minus the overpass that is still unfinished to June
30,2015 as scheduled .
Administrator Orendain Jr. said
that the COA denied the city
plan for the partial opening of the IBT since it the entire project is not
yet 100 percent (100% ) complete.
Although the IBT building is 100 % completed the contractor
has not completed the overpass that would allow people to cross the street to
and from the IBT.
According to Orendain, The COA has ruled that the project
should be 100 percent (100%)
complete before it can be opened to the public .
“Mandated del
COA no pwede abri partial , “ Orendain said.
“All the while we thought that because the building is completed pwede ya usa . Nuay kita
pensa it will happen that way , “ Orendain added.
As this developed, Orendain said that they already met with
contractor and the City Engineer’s Office headed by Engr. Luis Vicente
Despalo to expedite the completion of the “over pass” with in a
period of one (1) month.
Orendain said that they need about P 240,000 which is
not provided in the contract on the Zamcelco line that hamper the over
pass.
Orendain said that they already made the estimate on that
matter.
In other development, Orendain said that in as far as the
building is concern everything is completed except for some additional
improvement like to put a grills on the windows .
Orendain also said that about 50’s personnel will be deployed for
the operations of the IBT made up by , some 40’s on “job
order” personnel as man power, five (5) foreman and five (5) operators
for the CCTV cameras. (ZNS)