ZAMBOANGA
CITY (ZNS) –Social Welfare and Development Secretary Corazon “Dinky” Soliman
was optimistic Friday, September 5, that the Joaquin F. Enrique Memorial Sports
Complex in Baliwasan can be cleared of internally displaced persons (IDPs) by
December 15.
Sec.
Soliman said the sports complex is presently occupied only by 2,304 families or
12,476 individuals displaced by the Zamboanga siege almost a year ago.
Of the
number, she said the 1,658 families will be relocated to three transitional
sites—443 families in Tulungatung, 106 families in Sitio Buggoc and 225
families at Masepla in Mampang. The rest of the IDPs, about 646 families, can
still be accommodated in Bucco, given its expanded area.
Soliman
said the Dec. 15 deadline was a realistic enough to clear the grandstand of the
IDPs, now that the Cawa-Cawa shorelines have already been cleared of the IDPs,
following their relocation to Masepla transitional site and other temporary
shelters.
She
said efforts were underway to transfer all IDPs to temporary shelters before
all of them can be moved to permanent shelters, which are under construction by
the National Housing Authority.
Meanwhile,
the DSWD secretary said the agency had already spent a total of P363,946,629 in
various forms of assistance extended to the IDPs since the siege broke out on
Sept. 9, 2013.
The
amount did not include the P1.6 billion allocated by the national government
for the construction of permanent shelters and the Home Materials Assistance at
P30,000 each affected family. The Department of Public Works and Highways
(DPWH) has also its separate budget for the construction of road networks and
waterways.
Sec.
Soliman admitted though that almost a year had passed since the siege yet there
are still many things to be done to rebuild the affected areas much better than
they were before the siege. “But, the efforts have shifted (maybe slowly but
constantly) from response to recovery and reconstruction.”
She
said the transfer of Sama Badjao families from Cawa-Cawa shorelines to Masepla
may have been delayed by one week, but what was important the boulevard is now
cleared of IDPs. The next target is the grandstand one of before Dec. 15, 2014.
(Vic Larato) (091514)